オンサイト・オフサイトのコンクリート施設建設プロジェクトにおける気候・コスト性能の比較:ドイツのケーススタディ

Comparing Climate and Cost Performance of On- and Off-Site Concrete Facility Construction Projects: A German Case Study (原題)

Timm Draeger, C. Peper, Panagiotis Spyridis

Sustainability📚 査読済 / ジャーナル2026-10-12#炭素会計Origin: EU経営インパクト: コスト削減対象セクター: construction
DOI: 10.3390/su182010359
原典: https://doi.org/10.3390/su182010359
📄 PDF

🤖 gxceed AI 要約

日本語

ドイツ北部の実産業建築を対象に、現場打ち・完全プレキャスト・セミプレキャストのコンクリート躯体システムを、同一機能単位で直接コストと建設段階の embodied carbon(EN 15978 A1–A5)で比較した。直接コストは最大62.7%差が生じる一方、炭素は最大5.1%差にとどまり、感度分析ではその差の符号すら変わり頑健でない。材料生産が炭素の87–94%を占め、建設工法の選択は主に経済的判断であり、炭素削減は材料対策で対応すべきと結論づける。

English

Using a real industrial building in northern Germany, this study compares cast-in-situ, fully precast, and semi-precast concrete systems on identical functional units for direct cost and construction-phase embodied carbon (EN 15978 A1–A5). Direct costs vary by up to 62.7%, while embodied carbon differs by at most 5.1% and is not robust under sensitivity analysis. Material production accounts for 87–94% of carbon, so system choice is mainly economic and carbon must be tackled through materials.

Unofficial AI-generated summary based on the public title and abstract. Not an official translation.

📝 gxceed 編集解説 — Why this matters

日本のGX文脈において

日本では建設業のScope 3(カテゴリ1・2)や embodied carbon 開示、SSBJ対応が進む中、工法選択と炭素削減の切り分けは実務的に有用。ただし欧州規格EN 15978ベースであり、国内のLCA・炭素会計制度との接続には追加検討が必要。

In the global GX context

As global disclosure frameworks (ISSB, CSRD, TCFD) push embodied carbon into scope, this paper offers a rare same-project comparison showing that construction-method choice is cost-driven while carbon hinges on materials. It supports the case for material-focused decarbonization levers and transparent uncertainty reporting in building LCAs.

👥 読者別の含意

🔬研究者:同一機能単位でのコスト・炭素比較手法と感度分析の枠組みは、建設LCA研究の頑健性評価に応用できる。

🏢実務担当者:工法選定はコスト主導であり、炭素削減はセメント量など材料調達で狙うべきという実務的示唆。

🏛政策担当者:建設段階炭素の規制設計では、工法より材料(セメント)への介入が効果的である可能性を示す。

📄 Abstract(原文)

Selecting a reinforced concrete construction system is usually justified either economically or environmentally, and the two perspectives are rarely derived from the same project data. It therefore remains unclear whether the cost-optimal and the carbon-optimal choice coincide, and whether the differences between the systems are large enough to be distinguished from the uncertainty of the underlying assumptions. This study addresses that question for a real industrial building in northern Germany. Cast in situ, fully precast, and semi-precast systems were compared for the walls, slabs, and beams of a technical building, using contractor cost calculations and supplier quotations for the direct construction costs, and project-specific material quantities with generic emission factors for the construction-phase embodied carbon (modules A1–A5 of the European Norm EN 15978), both based on identical functional units. The direct costs differ substantially: the semi-precast double wall was 27.2% and the filigree slab 50.3% cheaper than their cast in situ equivalents, the fully precast wall and slab were 46.0% and 62.7% more expensive, and precast beams were 15.4% cheaper. The embodied carbon results differ by at most 5.1% between any two alternatives, and a one-at-a-time sensitivity analysis over ten parameters shows that this difference is not robust, since its sign changes within plausible parameter ranges; the cement content of the plant concrete is the dominant uncertainty. Material production accounts for 87% to 94% of the total in every case. The choice of construction system is therefore primarily an economic decision, whereas embodied carbon has to be addressed through material-related measures rather than through the construction method.